Week Date Activity
     
2 28-Jan  
    Clarify Project Constraints, Data Collection
    First Architectural Concept Sketches
    Cyber Discussion in ThinkTank on topic:
    "Can This Profession be saved?"
    Work on AEC Project Solutions
     
3 1-Feb Work on AEC Project Solutions - first A concept
     
4 8-Feb Work on AEC Project Solutions - first E, C, LCF concepts
     
5 15-Feb Second Alternative A,E,C concepts
     
6 22-Feb AEC Project PPT for reviews and crits
     
                  7 and 8 2/25-3/10, 2007 Work on AEC Project Solutions
     
9 March 10-13, 2008 EACH team schedules 2 Dry Runs
  14-Mar Winter Cyber Project Presentation
     
Spring Quarter    
10 4-Apr Project Web Doc Phase 1: Concept Dev.
    Work on details, analysis, 3D model, cost, schedule
11 11-Apr AEC Teams Prep PPT file for Fishbowl 
    Work on details, analysis, 3D model, cost, schedule
12 11-Apr AEC Teams review and integrate Fishbowl feedback
    Work on details, analysis, 4D model, cost, schedule
13 19-Apr No Class - Project team work
     
14 25-Apr NO CLASS - PROJECT WORK
     
15 5/5-8/2008 EACH AEC Team schedules 2 dry runs
  9-May Final Presentation and Party Celebration
     
16 16-May Web Project Document - Phase II: Project Development