NetDB Sybase to Oracle Port Project Home
  Home    Plan    Status    Documentation  

Here are the pages for all things concerning the NetDB port from Sybase to Oracle.

Scope

Convert the existing Sybase-based NetDB system to an Oracle-based system, while maintaining full functionality, taking advantage of appropriate Oracle features, and laying the groundwork for IPv6 support.
Project Completion (current best guess)
June 1, 2006.
Scheduling
Here is where this port fits into the current plans:
    Add "Node State" to current NetDB    2005-01-01 - 2005-08-01  Complete! (7/25/2005)
    Port to Oracle                       2005-01-01 - 2006-06-01  Complete! (6/01/2006)
    Finish CLI                           2005-06-01 - 2005-10-01  Complete! (8/10/2005)
Staffing
Here's the current level of staffing:
    Committed:  Dmitri     100%  These are the normal work assignments
                Joel       100%  for these people.
                Rob         50%
                Gaby        50%
                Sunia       10%

    Approved:   Ganapathy   For "Node State" implementation, remainder of CLI.
                Outsource   As necessary/expedient for port.


Updated: June 20, 2006